![]() |
|
|
Each month AUA will feature an outstanding Underground Project currently under construction, featuring its unique aspects in terms of technology, location, function, etc. Contact AUA to nominate projects. This month's Featured Underground:
MetroWest Water Supply Tunnel ProjectGreater Boston, Massachusetts
|
|
A turn of the faucet is the journey's end for water travelling halfway across Massachusetts to the homes of nearly 2.5 million people and over 5,500 businesses in communities served by the Massachusetts Water Resources Authority (MWRA). MWRA operates an elaborate system of over 400 miles of water tunnels and distribution mains, which feed another 6,700 miles of water distribution pipes, owned and operated by individual communities. This system is in its sixth decade of service and is in great need of repair. To avert the damage that could be caused by a major break or failure and to provide the missing redundancy that this region needs for basic health and safety, MWRA is building the MetroWest Water Supply Tunnel (MWWST). Constructing this project over the next five years will enable MWRA to upgrade its water transmission system, which was originally designed in the late 19th century, to a 21st century system that will serve Massachusetts residents for decades to come.
THE HULTMAN AQUEDUCT As a result, Greater Boston is the only major American metropolitan area to rely on a single water supply conduit to deliver over 85% of its drinking water. Without a backup system in place, routine repairs and proper maintenance work cannot be performed, leaving the Hultman in a steadily deteriorating state. Its structural integrity is diminishing: leaks, aging valves and joints, corroding steel and concrete are just a few of its problems. The older the pipe gets, the greater the possibility of a critical break or failure with serious public health and economic consequences. According to experts, the economic impact of a water supply interruption could be $65 to $100 million per day. Moreover, the risk to public health and public safety could not be measured in monetary terms.
MWWST WILL ANCHOR THE SYSTEM The IWSIP begins with increased protection of watersheds and the water quality of source reservoirs - vast natural resources that safely yield approximately 300 million gallons water per day. A new drinking water treatment plant, expected to be complete in 2003, will be built at Walnut Hill in Marlborough. This facility will employ enhanced water treatment technology, able to treat up to 405 million gallons of water, in compliance with state and federal regulations, each day. This treated water will be sent through the MWWST to customer communities, via the City Tunnel. The MWWST will also carry treated water to two covered distribution storage tanks in Weston. MWRA is building these tanks (in addition to three that will not connect directly to the MWWST) to replace uncovered open distribution reservoirs, which are vulnerable to contamination from airborne pathogens and algae growth. The new storage facilities will allow MWRA to maintain a protected supply of water for summer water peaks and emergency demands (such as fire-fighting flows), without resorting to putting old brick aqueducts into service. After the MWWST is complete and tested for safety and performance, the Hultman will be taken off line and rehabilitated, providing system redundancy, further strengthening MWRA's capacity to deliver water to residents, businesses, hospitals and industries - even when the MWWST needs to be maintained or repaired.
MWWST LOGISTICS AND SAFETY
MWWST CONSTRUCTION: A SYSTEM OF CONNECTIONS The East Heading will extend 6.6 miles under Wayland and Weston, where it will connect to the Eastern Tunnel Segment, which will end at Shaft W in Weston. Along the way, the Eastern Tunnel Segment will be connected by two shafts to the new Norumbega Covered Drinking Water Storage Facility. Excavation of Shaft 5A, Weston, is complete. It will serve as the work location for connection of Shaft W to the new Norumbega and Loring Road Covered Drinking Water Storage Facilities. The West Heading will extend 5.3 miles under Framingham into Southborough where the tunnel will connect at Shaft E. Shaft E is being excavated under the Western Tunnel Segment. The 4.7-mile Western Tunnel Segment will be mined from Shaft E continuing under Southborough to Shaft D in Marlborough. At Shaft D, the MWWST will be connected to the new Walnut Hill Water Treatment Plant. The MWWST and the new treatment plant are planned to be complete in 2003.
PUBLIC PARTICIPATION Public participation has been instrumental in developing Memoranda of Agreement (MOAs), addressing project host communities' environmental and safety concerns. Each MWWST contractor is required to comply with these agreements. As MWRA's MWWST Construction Manager, Stone and Webster employs personnel who help enforce the MOAs by monitoring all construction activities. Continued coordination between MWRA and working groups will help to resolve any concerns that may arise during MWWST construction. As the project progresses, meetings will be held periodically in each impacted Community. Large public improvement projects and their host communities benefit when citizen interest groups, municipal officials and other interested parties maintain an open, regularly scheduled forum for status updates. This approach facilitates communication at all levels and allows for rapid response to community concerns. The goal of MWRA's commitment to effective mitigation measures and community agreements is to avoid or minimize any potential adverse impacts to communities or the environment.
PAST FEATURES: Addison Airport Tunnel Project - New toll road tunnel will ease Dallas traffic congestion Los Angeles Metro Red Line - Santa Monica Mountains Tunnels The Central Artery/Tunnel Project in Boston, Massachusetts. The Central Artery, a six-lane elevated road built in the 1950s to handle about 75,000 vehicles a day, is now jammed with over 190,000. A few years ago, with the specter of 14-15 hour a day traffic jams looming in our region's future, the Massachusetts Highway Department began construction of the Central Artery/Tunnel Project. |
|